24/00772/FUL
|
Flat roof overlay at the rear of Holy Cross School, including, new insulation layer, new roof light, refurbished vertical spigot outlets, raised parapet wall, reduction in widow height (abutting wall) and introduction of a Permanent Counterweighted Guardrail System (PCGS).
|
Holy Cross Catholic Primary School Beaumont Road Plymouth PL4 9BE


Collapse All|Expand All
Climate Emergency
Consultation Date: Tue 25 Jun 2024
Historic Environment
Comment Date: Wed 24 Jul 2024
24-00772-FUL - Holy Cross Catholic Primary School - Historic Environment Consultation.docxLead Local Flood Authority
Comment Date: Tue 16 Jul 2024
LLFA consultation response 24.00772.FUL.pdfPublic Protection Service
Comment Date: Mon 15 Jul 2024
FROM: Public Protection Service (951515)RESPONSE DATE: 15/7/2024
APPLICATION NO: 24/00772/FUL
SITE: Holy Cross Catholic Primary School Beaumont Road Plymouth
PL4 9BE
DEVELOPMENT: Flat roof overlay at the rear of Holy Cross School, including,
new insulation layer, new roof light, refurbished vertical spigot outlets, raised parapet wall, reduction in widow height (abutting wall) and introduction of a Permanent Counterweighted Guardrail System (PCGS).
CONDITION NO: DC/1160/SFMO18MM06302
Observations: No comments
Summary of response: Approval
Highway Authority
Comment Date: Tue 25 Jun 2024
There are no objections to this application from a LHA viewpoint.