Planning – Application Comments

Help with this page (opens in a new window)

24/01318/MJR | Pre-application for condition (14) discharge of a phased mixed use development of 136 affordable homes (Class C3) and 628sqm of flexible (Class E) commercial units | Land At Bath Street Plymouth PL1 3LT
  • Print summary icon
  • Total Consulted: 2
  • Consultees Responded: 1
  • View all comments icon

Search Filters

Collapse All|Expand All

Urban Design

Consultation Date: Fri 25 Oct 2024

Highway Authority

Comment Date: Wed 20 Nov 2024

Plymouth City Council
Strategic Planning & Infrastructure

Transport Planning Team
Ext: 01752 307813
Date: 19th November 2024
Ali Wagstaff
Development Management
Strategic Planning & Infrastructure
Floor 2
Ballard House

Dear Ali

Highway Authority Consultation Response to a Planning Application


APPLICATION NO: 24/01318/MJR

SITE: LAND AT BATH STREET, PLYMOUTH

DEVELOPMENT: Pre-application for condition (14) discharge of a phased mixed use development of 136 affordable homes (Class C3) and 628sqm of flexible (Class E) commercial units


Observations:

Since the granting of planning permission for the development (app no 22/02109/FUL), the LHA have engaged with the applicant's highways consultant on the proposed alterations to the highway which are intended to be delivered by way of a Section 278 Agreement.

Following an exchange of emails during July and August 2024 (which included the submission of an RSA), the LHA are now content with the general layout and changes to the highway as shown on submitted External Works Plan. However, I would add that the plans submitted to and approved by the LHA related to the General Arrangement along with the Signing and Lining Details.

Feedback from the LHA on the proposals did not go as far as commenting upon or approving any of the Hard Landscaping Details (which the LHA have already stated previously would also require sign-off by the LPA). As such this element of the highway works are still to be formally agreed and as such the LHA could not recommend the discharge of Condition 14 on this basis.

I hope these comments are helpful.

Regards


Scott Smy
Transport Development Coordinator

Officer authorised to sign on behalf of the Service
Director for Strategic Planning & Infrastructure